Get premium membership and access revision papers with marking schemes, video lessons and live classes.
  OR
Processing. Please wait.

 Form 4 Mathematics Paper 1 Exam Revision Questions With Answers Set 3

Twenty four men working at the rate of 10 hours a day take 16 days to complete a job. How long would 40 men working at the rate of 8 hours a day take to complete the same job?

 (1m 55s)
785 Views     SHARE

|