 Form 3 Mathematics Compound Proportions and Rates of Work Questions and Answers

A construction firm has two tractors T1 and T2. Both tractors working together can complete piece of work in 6 days while T1 alone can complete the work in 15 days. After the two tractors had worked together for four days, tractor T1 broke down. Find the time taken by tractor T2 to complete the remaining work.

 (7m 4s)