 Form 3 Mathematics Compound Proportions and Rates of Work Questions and Answers

A construction firm has two tractors #T_1# and #T_2#. Both tractors working together can complete piece of work in 6 days while #T_1# alone can complete the work in 15 days. After the two tractors had worked together for four days, tractor #T_1# broke down. Find the time taken by tractor #T_2# to complete the remaining work.